Combining the demand for electricity and gas, the energy demand of the institute’s building in the Breslauer Strasse in Karlsruhe in 2023 amounted to almost 700 megawatt hours (MWh) per year. Until 2022, roughly the same amount of gas and electricity was required.
In addition to the mains supply, the institute’s building also drew power from two combined heat and power units (CHP), which together covered an average of twelve percent of the energy consumption in the period 2014 to 2022. In 2023, this share fell to three percent as the CHPs operated intermittently due to outages and were run at a reduced capacity due to the shortage of gas in the fall of 2022.
The number of employees does not seem to have a major impact on the energy consumed at the institute. In 2014/2015, some employees were relocated to a different building due to asbestos removal in the west wing, but energy consumption remained more or less constant. During the COVID-19 years between 2020 and 2022, when employees were required or encouraged to work from home, there was an eleven percent drop in electricity consumption. Gas consumption, however, rose by 18 percent.
From March 2020, additional offices were rented in Karlsruhe Technology Park (Emmy-Noether Strasse). 13 people worked there to start with. Over time, more office space was rented. A few offices were added at the additional locations in Heilbronn (from January 1, 2023) and Berlin (from October 2024). The energy consumption for these locations has not yet been (fully) determined. The focus here is therefore on the energy consumption of the institute’s building in Breslauer Strasse.
The gas demand in 2023 for the institute’s building and including the gas required for the CHPs was 230 MWh. Deducting the gas needed to generate electricity results in 215 MWh gas required for heating. This means the energy required for heating is significantly below the figures for 2022 (283 MWh) and 2021 (362 MWh). This is because Fraunhofer ISI took short-term gas-saving measures in the collective effort to avoid a gas shortage in the winter of 2022/2023. For example, the heating in one whole corridor was turned down to 16°C. The employees affected including the institute’s directors, moved to a different corridor over this winter. In addition, employees were made more aware of this issue and among other things were advised to only heat their offices to a maximum of 19°C. Heating settings were adjusted, such as extending the overnight temperature reduction to include weekends. Retaining some of the less drastic measures also resulted in a decrease of gas consumption in the winter of 2023/2024 compared to the winter of 2021/2022. Hydraulic balancing was carried out in the fall of 2023 before the onset of the heating period. In the fall of 2024, the heating systems, which were more than 30 years old, were replaced by a combination of two air-water heat pumps (128 kW) and a gas condensing boiler (220 kW). The goal is to only use the gas boiler at low temperatures and to meet most of the building’s heating demand using the heat pumps. Before deciding to invest in the new system, different variants were compared in terms of their economic efficiency and CO2 emissions. The above mentioned variant was selected because of the short length of time remaining that Fraunhofer ISI will use the institute’s building – due to the planned new building.
Once a year, employees are given information about how to save energy on top of emails explaining how to heat correctly, posters about energy saving and short presentations at institute or work council meetings.